Municipal WWTP

Templemore SS

  • Design/Build/Operate Contract
  • 20 yr O&M Contract
  • P.E. 6000
  • 2 No. Treatment Streams incorporating Aerator Wheel (STM), Clarifier
  • On-site Sludge Thickening & Dewatering
  • Odour Control
  • Capital Works €3,400,000

Download Case Study

Bantry SS

  • M&E Contract
  • P.E. 6000
  • Treatment comprises of Screening/Grit Removal, Oxidation Ditch, Clarifier, Thickening & Dewatering
  • Odour Control
  • Nutrient Removal (0.5 mg/l NH4 & 2 mg/l P)
  • Capital Works €2,000,000

Download Case Study

Leitrim T&V DBO

  • Design/Build/Operate Contract
  • 20 yr O&M Contract
  • P.E. - 10 No. WWTP’s ranging from 100PE to 2,600PE
  • Package Type Treatment Systyem incorporating Aerator Wheel (STM), Clarifier etc.
  • 15 No. Outlying PS’s
  • On-site Sludge Thickening
  • Capital Works €10,400,000

Download Case Study

Carrick-on-Shannon

  • Design/Build/Operate Contract
  • 20 yr O&M Contract
  • P.E. 11,500
  • Fine Bubble Diffused Aeration System
  • On-site Sludge Thickening & Dewatering
  • 2 no. New PS’s & refurbishment of 7 no. PS’s
  • Capital Works €7,900,000

Download Case Study

Thurles Wastewater Treatment Plant Upgrading Works

  • Plant Upgrade DB Contract
  • PE 15000
  • €1.7M Capital Works
  • Inlet Works
  • FBDA Aeration
  • Sludge Reception Centre
  • ICA/SCADA

Download Case Study

Castlerea Sewerage Scheme

  • M&E Contract
  • PE 5000
  • Capital Works €3.0M
  • Extended Aeration FBDA/Submersible Mixers
  • Sludge Dewatering by Centrifuge 18% DS
  • Odour Control/Biofilter
  • Discharge Standard 25/35 BOD/SS and 2mg/Lp

Download Case Study

Ballina Main Drainage Wastewater Treatment Plant

  • Plant Upgrading/M&E Contract
  • €2.0M Capital Works
  • PE 35000
  • 6 Pumping Stations
  • GRP-roofed Primary Tanks
  • FBDA Aeration
  • P-Reduction
  • Odour Control
  • ICA/SCADA

Download Case Study

Monasterevin Sewerage Scheme M&E Installation, Operation & Maintenance Contract

  • M&E Contract
  • Short Term O&M Contract
  • P.E.9000
  • Extended Aeration / FBDA
  • P reduction to 0.7 mg/l
  • Odour Control
  • Capital Works €2,200,000

Download Case Study

Shannon Airport Design Build Operate Contract

  • DB & 20yr O & M Contract
  • PE 7500
  • Performance Management System ( PMS )
  • BOD : 20 / SS : 30 / P : 2 / TN : 10
  • SCADA System for WWTW & Outlying PS
  • Capital Works €2,300,000

Download Case Study

Ballyheigue Sewerage Scheme Wastewater Treatment Plant

  • New Plant M&E Contract
  • €1.85 Capital Works
  • PE 4300
  • FBDA Aeration
  • Odour Control
  • UV Disinfection/Blue Flag Beach
  • ICA/SCADA

Download Case Study

Carlow Town Wastewater Treatment Plant Upgrading

  • Plant Upgrading/M&E Contract
  • PE 36000
  • Capital Works €800K
  • FBDA to replace Surface Aeration
  • P-reduction by Simultaneous Precipitation
  • Discharge Standard 25/35 BOD/SS and 2mg/l P

Download Case Study

Bunclody SS

  • Design/Build/Operate Contract
  • 20 yr O&M Contract
  • P.E. 6500
  • 2 No. Treatment Streams incorporating Aerator Wheel (STM), Clarifier
  • On-site Sludge Thickening & Dewatering
  • Odour Control
  • Capital Works €2,850,000